SOCAR将对天然气加工和石化综合项目做出FID

   2019-04-25 石油设备网Ryan75100
核心提示:Recall that SOCAR thought about building a gas processing plant and a petrochemical complex GPC back in 2015. In January 2015, the project showed great interest in companies such as Shell, Total and several oil companies from Saudi Arabia. However, in the

石油设备网讯 据Neftegaz.RU巴库4月23日消息称,关于天然气加工(GPP)和石化综合企业阿塞拜疆SOCAR GPC项目的最终投资决定(FID)将于2019年第4季度做出。

建设工作将于2020年第一季度开始,综合设施将于2023年第三季度投入使用。

在GPC项目中,计划在巴库天然气处理和石化综合设施外15公里处建设一个产能约为100亿立方米/年的天然气处理厂,建设一个产能为61万吨的气动乙烯裂解装置,一个产能为13万吨的丙烯装置和产能60万吨聚乙烯装置。

SOCAR GPC项目下的工程和建设工作由HQC提供,HQC在设计、采购和建设项目方面拥有丰富的经验,并在阿塞拜疆公司的支持下,基于世界领先的许可方所准备的项目。

据初步估计,该项目的成本约为40亿美元。荷兰国际集团、中国国家开发银行和俄罗斯天然气工业银行担任SOCAR GPC的财务顾问。美国文森艾尔金斯律师事务所是国际级别的法律顾问,PSG是阿塞拜疆的法律顾问。

回想一下,早在2015年,SOCAR就曾考虑建造一座天然气加工厂和一座石化综合设施GPC。2015年1月,壳牌、道达尔以及沙特阿拉伯的几家石油公司对该项目表现出浓厚的兴趣。然而,在2015年春天,由于聚乙烯和聚丙烯的世界价格下跌,这些公司放弃了他们的计划。2016年2月,由于油价低迷,SOCAR暂停了该项目。然而,2016年5月,该公司表示,他们保留了该综合体的建设计划,该项目只是暂时冻结。2016年6月,为了使该项目对潜在投资者更具吸引力,SOCAR将OGPC天然气化工综合设施的建设成本从70亿美元降至40亿美元。并于2017年11月,SOCAR GPC副总干事F. Akhmedov保证,SOCAR GPC天然气加工和石化综合项目的FID 将于2018年5月至6月通过。然而,这个项目被推迟了,FID也没有被通过。

曹海斌 摘译自 Neftegaz.RU

原文如下:

SOCAR will take the final investment decision on the gas processing and petrochemical complex project by the end of 2019

Baku, Neftegaz.RU. The final investment decision (FID) on the project of a gas processing (GPP) and petrochemical complex SOCAR GPC will be made in the 4 th quarter of 2019.

Construction work will begin in the 1st quarter of 2020, and the complex will be commissioned in 3rd quarter 2023.

Within the GPC project plans to create 15 km from Baku gas processing and petrochemical complex, the capacity of which will be about 10 billion m 3/ year of gas per year, construction of a gas-operated ethylene pyrolysis unit with a capacity of 610 thousand tons, a propylene installation with a capacity of 130 thousand tons and a polyethylene installation with a capacity of 600 thousand tons.

Engineering and construction work under the SOCAR GPC project is provided by HQC, which has extensive experience in the design, procurement and construction projects, with the support of Azerbaijani companies based on projects prepared by the world's leading licensors.

The cost of the project, according to initial estimates, is about $ 4 billion. ING Bank, the State Development Bank of China and Gazprombank act as financial consultants to SOCAR GPC. American Vinson & Elkins is a legal advisor at the international level, and PSG is involved as a legal adviser in Azerbaijan.

Recall that SOCAR thought about building a gas processing plant and a petrochemical complex GPC back in 2015. In January 2015, the project showed great interest in companies such as Shell, Total and several oil companies from Saudi Arabia. However, in the spring of 2015, these companies abandoned their intentions due to the decline in world prices for polyethylene and polypropylene. In February 2016 SOCAR suspended the project due to low oil prices. However, in May 2016, the company said that they were retaining plans for the construction of the complex, and the project was only frozen temporarily. In June 2016, in order to make the project more attractive for potential investors, SOCAR reduced the cost of construction of the OGPC gas chemical complex from $ 7 billion to $ 4 billion. And in November 2017The Deputy Director General of SOCAR GPC F. Akhmedov assured that the FID for the project of the SOCAR GPC gas processing and petrochemical complex will be adopted in May-June 2018. However, the project was delayed and the FID was not accepted.

 

 
举报收藏 0打赏 0评论 0
 
更多>同类资讯
推荐图文
推荐资讯
点击排行
网站首页  |  关于我们  |  联系我们  |  用户协议  |  版权声明  |  隐私政策  |  网站地图  |  排名推广  |  广告服务  |  积分换礼  |  网站留言  |  违规举报  |  苏ICP备12075075-1号